City Council award Contract No. 19-06, to Rino Construction on their low bid of $391,260.00 plus Washington State sales tax of $4,552.50 for a total contract price of $395,812.50 for Project No. CP1804, Auburn Way North Sidewalk Improvement Project.
Background for Motion:
Background Summary:

The City received seven (7) responsive bids and the low bid was approximately 9.30% below the engineer’s estimate.  Staff has performed reference checks and other verifications to determine that Rino Construction meets the responsible bidding criteria and recommends award.

 

The purpose of the project is to construct missing sections of sidewalk, construct ADA improvements, construct a Rectangular Rapid Flashing Beacon (RRFB) on Auburn Avenue just south of 5th Street NE, and install LED lighting along Auburn Way North.

 

Construction is expected to begin in May 2019 and be completed by August 2019.

 

A project budget contingency of $25,200.00 remains in the 328 Capital Improvement fund and a project budget contingency of $12,950.00 remains in the 462 Storm Drainage Fund.

Reviewed by Council Committees:
Councilmember: Staff: Gaub
Meeting Date: April 1, 2019 Item Number: CA.D