Administrative Recommendation:
City Council approve Final Pay Estimate No. 7 to Contract No. 17-02 in the amount of $48,445.92 and accept construction of Project No. CP1507, Auburn Way North Preservation.
Background for Motion:
Background Summary:

The Auburn Way North Preservation Project (22nd Street NE to 45th Street NE) included grinding and overlaying the asphalt pavement, replacement of curb/gutter and concrete flatwork, construction of storm drain pipe and structures, removal and replacement of fire hydrant assemblies, installation of a new traffic signal at 37th Street NE, modifications to existing traffic and pedestrian signals, channelization, installation of induction loops, traffic control, right-of-way restoration, and signage.

A project budget contingency of $6,237.00 remains in the 462 Storm Fund.

A project budget contingency of $3,505.00 remains in the 460 Water Fund.

A project budget contingency of $4,575.00 remains in the 461 Sewer Fund.

A project budget contingency of $112,638.00 remains in the 105 Traffic Fund.