AGENDA BILL APPROVAL FORM

 
Agenda Subject:
Public Works Project No. CP1710
Date:
January 29, 2018
Department:
CD & PW
Attachments:
Final Pay Estimate No. 5
Vicinity Map
Budget Status Sheet
Budget Impact:

Administrative Recommendation:
City Council approve Final Pay Estimate No. 5 to Contract No. 17-17 in the amount of $7,622.23 and accept construction of Project No. CP1710 Citywide Sidewalk Repair and Improvement.
Background for Motion:
Background Summary:

The purpose of this project was to add sections of sidewalk that are missing from the pedestrian network, reconstruct sections of existing sidewalk, add new and reconstruct existing curb ramps to meet ADA standards, and reconstruct existing driveways.

A project budget contingency of $59,666.00 remains in the 328 Capital Improvements Fund.

Reviewed by Council Committees:
Councilmember: Staff: Gaub
Meeting Date: February 5, 2018 Item Number: CA.D