Change Order No. 2 covers additional costs for traffic control labor and for temporary pavement markings that were required during the time the existing pavement on Auburn Way North between 22nd Street NE and 45th Street NE was ground off awaiting for the new pavement to be placed. With Auburn Way North being a highly traveled corridor, and the requirement to maintain traffic during work operations, the traffic control labor and temporary markings for the various lane adjustments required was much greater than anticipated.
A project increase of $100,000.00 within the 105 Street Preservation fund will be necessary, however it will not require a budget adjustment since it is anticipated that the total budgeted expenditures in the 105 Street Preservation fund will not be exceeded this year. |