AGENDA BILL APPROVAL FORM

 
Agenda Subject:
Public Works Project No. CP1415
Date:
December 11, 2017
Department:
CD & PW
Attachments:
Budget Status Sheet
Final Pay Estimate No. 12
Vicinity Map
Budget Impact:
Current Budget: $0
Proposed Revision: $0
Revised Budget: $0
Administrative Recommendation:
City Council approve Final Pay Estimate No. 12 to Contract No. 16-12 in the amount of $22,674.76 and accept construction of Project No. CP1415, West Main Street Multi-Modal Corridor and ITS Improvements.
Background for Motion:
Background Summary:

This project repurposed the existing West Main St. corridor and built the Intelligent Transportation System (ITS) improvements. Roadway improvements included converting the existing four-lane West Main St. roadway section to a three-lane section including center two-way left turn lane with new bike lanes, new sidewalks, street trees, and new LED street lighting improvements between West Valley Highway and the Interurban Trail. ITS Improvements included interconnecting and coordinating traffic signals from C St. NW along West Main St. to West Valley Highway (WVH), south to 15th St. SW including two interchanges with SR-18 and one with SR-167.

 

A project budget contingency of $64,004.00 remains in the 102 Arterial Street Fund.

Reviewed by Council Committees:
Councilmember: Staff: Snyder
Meeting Date: December 18, 2017 Item Number: CA.D